Setting up a kids indoor playground is a rewarding investment—but only if the planning and installation process is well managed. From the moment you confirm your order to the day your first customers walk in, success depends on clear timelines, the right team coordination, and thoughtful preparation.
At Qilong Amusement Equipment Co., Ltd., we’ve supported thousands of playground projects across the globe. Whether it’s a small 30㎡ toddler zone or a multi-functional china commercial indoor playground, here’s a step-by-step guide to help you plan a smooth and successful installation.
Order Confirmation and Design Finalization
(Week 0–2)
✅ What Happens:
Finalize equipment list and layout based on your floor plan
Approve 3D renderings and design themes
Sign contract and issue down payment
Tips:
Share accurate site measurements and ceiling height
Confirm your local safety regulations (ASTM, EN, etc.) in advance
If needed, request modifications to suit columns, walls, or obstacles
🛠 Qilong supports full 3D planning and customization for any space size.
2. Production & Quality Control (Week 3–6)
✅ What Happens:
Material Preparation
Key materials like PVC, steel, wood, and foam are precisely cut and prepped for production.
Module Fabrication & Testing
All components are assembled, coated, and tested for structural strength and visual consistency.
Quality Inspection & Packing
Each item undergoes strict quality control before being safely packed for shipment.
Tips:
Ask your supplier for factory photos or production updates
If you're working on a tight deadline (e.g., opening event), notify the factory early
⏱ Average production time:
Soft play: 3–4 weeks
Trampoline park: 4–6 weeks
Rope/climbing course: 4–7 weeks
Logistics Planning & Shipment
(Week 6–9)
✅ What Happens:
Equipment packed in wooden boxes and stretch film
Booking and loading of container(s)
Shipment arranged (FOB/CIF) with full document support
Tips:
Secure your customs broker early
Ensure the delivery location is accessible for a 40’ container
Ask for the packing list in advance to plan unloading
🌍 Qilong ships to over 80 countries via sea, land, and air freight.
Site Preparation Before Installation
You should complete the following before installers arrive:
Floor is level, cleaned, and covered with protective layer (if required)
Power outlets, lighting, and air conditioning installed
All other construction or renovation work finished
Unloading path cleared and equipment moved indoors
Tips:
Indoor humidity should be under control (below 60%)
If you're hiring your own labor, ask for the installation manual in advance
On-Site Installation
(1–6 Weeks, Depending on Size)
✅ What Happens:
Steel structure assembled
Panels, nets, and slides installed
Safety checks and fine adjustments completed
Team Structure:
Lead installer + 2–6 local assistants
Daily progress and coordination with your project manager
Tips:
Ensure good lighting and ventilation
Allow extra buffer time if your site is above the ground floor
Schedule inspections or fire safety checks after installation
🔧 Qilong can send a professional supervisor or full team depending on your location.
Final Testing and Opening Preparation
✅ Final checklist:
All areas cleaned and inspected
Emergency exits and signage checked
Safety mats, fences, and barriers confirmed
Play rules printed and displayed
Once approved, you're ready to open! Consider soft launching with a members-only event or family preview to generate early feedback and social media buzz.
Common Questions from First-Time Owners
Q1: Can I install the equipment myself? Yes, for small setups (under 200㎡), Qilong can provide manuals and remote video guidance. For larger or more complex playgrounds, we recommend professional supervision.
Q2: What if I find a missing or damaged part during installation? No worries—we’ll ship replacements promptly, and our engineers can guide you online.
Q3: How much space do I need for unloading and installation? A 40’ HQ container needs a clear space for delivery. We suggest having 100㎡ clear and dry for unloading materials.
Conclusion: Preparation Makes a Perfect Playground
With the right planning, building a playground is exciting—not overwhelming. Clear communication, coordinated teams, and realistic scheduling are the keys to a successful launch.
At Qilong Amusement Equipment Co., Ltd., we guide you at every step—from layout and production to shipping and installation. Whether you’re opening a small toddler play zone or a full-scale trampoline park, our global experience ensures a smooth setup every time.